Home -> Project Photos -> (Mundelein) Vineyard Church, Mundelein/Libertyville, IL

Vineyard Church - Mundelein/Libertyville, IL

Project in Progress (2003) Page 2

 

September 25, 2003 - Drywall is going up.

The framed sound and video booth (below)

 

September 29, 2003 - the rear wall is being drywalled & the side walls are taped and mudded.

...same day - the brackets & speakers are going up

It took a total of about 8 hours to install all 5 speaker brackets and speakers.

 

Here's the mount in the attic. These two photos (below) are courtesy the installers themselves (CCS Presentation Systems)

Center bass box bracket (below)t

 

Side horn bracket (below)

 

October 20-21, 2003
The room has been fully painted (walls and ceiling) and carpet has gone down. I (Blake) am now in the process of setting up the DSP for the main house system and monitor systems.

View from the mixer desk (below)

Thus far, the system adjustment and tuning is going quite well. Besides a few minor issues we've overcome, the main system sounds quite good. There will be tweaks and adjustments needed over the next year as the room dries out and as the audio operators become used to the room and system.

view from the front right corner to the rear left corner (soundbooth) (below)

 

 

 
This web page will be udated throughout the remainder of the project;
be sure to check back often!

copyright ©2003, All Church Sound